A section of concrete core wall left low to divert creek, Dam 2.
Roots, logs, and stumps taken from trench excavated for core wall, Dam 2.
Flowing well, Dam 2, flow 1 1/2 gallons per minute.
Setting forms for core wall, Dam 2.
Excavator cutting channel to divert creek, Dam 2.
Excavation, for diverting Juniper Creek, Dam 2.
Excavation, for diverting Juniper Creek, Dam 2.
Building temporary bridge across new creek channel, Dam 2.
Excavation, for core wall, Dam 2.
Excavation, Dam 2, S.E. portion looking N.W.