Date Published: July 23, 2006
3 years later, U.S. 521 section still incomplete
By SHARRON HALEY Item Staff Writer shaley@theitem.com
MANNING — A 250-foot section of U.S. 521 is holding
up completion of a widening project that began more than three
years ago.
Work on the portion of U.S. 521 between the
Sumter County line and Interstate 95 began June 9, 2003, and
was scheduled for completion in August 2005; however, problems
with the soil quality in a small section of the project have
stymied operations.
“Months ago, I was telling people
work on the project would be completed in the next couple of
months, but a 1,000-foot section of [U.S.] 521 has rutted,
causing delays and adding to the work of the contractor for
the project,” said Kevin Webber, Clarendon County’s resident
construction engineer with the South Carolina Department of
Transportation. “We’ve tested the soil, the base and the
asphalt in the DOT lab and in an outside lab to isolate the
problem and correct it.”
Webber said the test results
conflicted with one another and were unable to isolate the
problem.
To get to the base of the problem, Webber said
the contractor for the project removed the asphalt, dug one
foot and introduced a mixture of cement and a stone base on
top of four inches of dirt.
“This corrected the rutting
problem, but when we were testing for compaction, an area of
about 200 to 250 feet did not meet specifications,” he said.
“So, we’re actually back to the drawing
board.”
Although the problem area has been reduced, the
project is still behind schedule.
“It’s all in the
hands of our headquarters,” Webber said. “Our engineers are
working on what steps we take next.”
Recent heavy
construction off U.S. 521 near the section isn’t helping with
the problem, the resident engineer said.
“Heavy loaded
vehicles are taking a toll on the road,” he said. “It’s
definitely had an impact, but it shouldn’t have caused the
problem.”
Webber said the bulk of the problem lies in
the moisture content of the soil beneath the
asphalt.
“We’re building a road on soil with a high
clay content,” he said. “There’s moisture in clay. When the
road was built and set up, the soil was dry; now moisture is
seeping up through and out from under the road. We hoped the
concrete would bridge the gap and it worked for a portion of
the area, but we still have to find a solution for the
remaining 250 feet.”
Webber said soil conditions are a
hazard of road construction projects.
“You don’t know
what’s underneath the asphalt that’s there,” he said. “The
project is taking longer than what we would have liked, but we
don’t want to just put a band-aid on the problem. We want it
fixed right.”
According to the transportation
department’s Web site, the 250-foot portion of subgrade
failure falls within a two-mile section of construction on
U.S. 521. The cost of the two-mile project was $300,000;
however, transportation officials anticipate the cost will
rise because of the subgrade failure. The amount of the
increase won’t be known until the problem is
solved.
Contact Staff Writer Sharron Haley at shaley@theitem.com or
803-435-8511.
For updates on progress with the U.S.
521 widening project, visit http://www.scdot.org/ and click on the
Construction Updates link. From there, go to the blue box for
Projects By County and click Clarendon. Another blue box will
appear with links to the latest news on all portions of these
projects.
|

|
|

|
|