printer friendly format sponsored by:
The New Media Department of The Post and Courier

WEDNESDAY, MARCH 29, 2006 12:00 AM

Corps needs more time to evaluate port terminal

BY JOHN P. McDERMOTT
The Post and Courier

COLUMBIA - Originally set for August, approval of a $700 million port terminal proposed for the former Navy base in North Charleston is on hold until at least November to give federal regulators more time to evaluate the expansion.

The U.S. Army Corps of Engineers Charleston District said Tuesday it extended the time it needs to complete its final environmental impact statement for the project and a new port access road by 65 days, from late May to early August. That pushes the permitting agency's "record of decision" to mid-November.

The decision was based on feedback from the public about the routing of the new road, as well as questions from environmental agencies about the models being used to measure the project's impact on water and air quality, said Bernard S. Groseclose, president and chief executive of the State Ports Authority.

While the SPA would prefer a decision by the end of the summer, Groseclose told the authority's board members at a meeting in Columbia that the permitting delay was a minor setback.

"In conversations with the Corps and so forth, the key is if we can move forward with approval and not have any objections ... that would take us into court, we'd be better off," he said afterward. "That's how we're looking at it. In the long run, it'll probably be time well-spent to clear up questions."

Groseclose said the SPA will explore ways to make up for the lost time. The first, $600 million phase is expected to be ready in 2011 or 2012. "There are certainly elements of the project we can speed up," he said. "That's my hope - that we can do some of that and keep the overall project on track."

The Corps has twice given the public extra time to comment on the five potential routes for the port access road between Interstate 26 and the proposed container yard. Initially, the Department of Transportation sought more time because it said some key questions have not been adequately addressed. The comment period now ends April 19.

"It all speaks to the relative importance of this project," said Nat Ball, project manager with the Corps.

"It's important to realize the process is working," said Lt. Col Ed Fleming, commander of the Corps' Charleston District.

In the works for more than a decade, expansion of the increasingly crowded Port of Charleston has been beset by delays.

In the 1990s, the SPA wanted to build a massive cargo facility on Daniel Island, but a groundswell of opposition forced it to refocus its efforts on 280 acres at the south end of the old Navy base. Plans call for a three-berth terminal that will be capable of handling up to 1 million 20-foot-long containers a year.

 

If you go

The Corps and the DOT are holding the final public workshop regarding the road project from 4:30-7 p.m. Thursday at the Military Magnet Academy, 2950 Carner Ave., North Charleston.

 

Jessica Van Egeren contributed to this report. Contact John McDermott at 937-5572 or jmcdermott@postandcourier.com.


This article was printed via the web on 3/29/2006 3:11:37 PM . This article
appeared in The Post and Courier and updated online at Charleston.net on Wednesday, March 29, 2006.